The Roxwell Brook is a right-bank tributary of the River Can draining a catchment area of approximately 36.6 km2, including the Newland Brook catchment. During June 2016 the village of Roxwell suffered severe flash flooding and 8 properties were directly affected by flood water. The Roxwell Brook Natural Flood Management (NFM) project was initiated to investigate the potential for reducing the future risk of such flooding.

 

Flooding Roxwell 2016 Dan boyle 4M

Flooding in Roxwell village c/o Dan Boyle

 

The construction of a number of natural flood management interventions upstream of the village is intended to slow the flow and intercept water, in particular during storm downpours across the catchment.

 

Roxwell Brook Leaky Dam installation April 2019 Darren Tansley 14

 Construction of leaky dams, Roxwell Brook

 

Phase one involves the installation of 10 woody debris log jams – 5 along Roxwell Brook and another 5 in Newland Brook. Phase two requires the design and building of more substantial off-channel water interception to allow temporary storage of water away from the main channel during peak flows. The aim is to reduce peak water levels and slow the arrival of water at pinch points such as road bridges in the main village downstream.

 

Roxwell Brook Leaky Dam installation April 2019 Darren Tansley 22

 Completed leaky dam, Roxwell Brook

 

The work is being delivered by Essex Wildlife Trust working with a variety of riparian landowners and the local resident’s Roxwell Flood Prevention Group. Funding and support from the Environment Agency is a key driver for this project which is due to be completed by 2020.

 

RBD/catchment/river/tributary

River Can

WFD water body status

Project type

Natural Flood Management

Project lead

Essex Wildlife Trust

Contact for more information

This email address is being protected from spambots. You need JavaScript enabled to view it.

Project partners

Environment Agency, Roxwell Flood Prevention Group

Funding source

Environment Agency

Project start

01/04/2018

Website key stakeholders:

Environment Agency logo      Essex Wildlife Trust logo           

Design by LTD Design Consultants and build by Garganey Consulting based on an original concept by Herts and Middlesex Wildlife Trust